Find the hidden costs in construction change orders.
This calculator is based on standard construction industry practices for change order pricing (e.g., principles outlined in AIA Document G701 and consensus docs).
Why hidden costs matter: Practitioners often only charge for direct materials and field labor. However, processing a change order requires administrative time (estimating, drawing changes, procurement) and often delays the critical path, accruing daily general conditions overhead or liquidated damages.
Formula: Total Price = (Materials + (Labor Hrs * Rate) + Equipment + (PM Hrs * Rate) + (Delay Days * Daily Cost)) * (1 + (Markup % / 100))